Probing and convergence measurement

View at publisher
Authors: Nick Barton
Cited by: 0

Abstract

The big investment in a sophisticated TBM and the expectation of mostly rapid advance rates can each be spoiled by the unexpected delays caused by ‘unexpected ground’. Only a few percent of the total length of a tunnel may be ‘unexpected’, yet these few percent could double the construction time in some cases. Although deep tunnels are notoriously difficult to predict, regular probe drilling during cutter change and maintenance shifts could largely remove the unexpected; especially if performed with two slightly diverging probe holes.

Fields of Study & Subjects

Tunneling and Rock Mechanics Geotechnical Engineering and Analysis Geotechnical Engineering and Underground Structures

Publication details

Journal / source
CRC Press eBooks
Pages
123–128
Publication date
19 January 2026
Language
EN
Document type
Book chapter