Summary of common geotechnical problems

View at publisher
Authors: Nick Barton
Cited by: 0

Abstract

TBM tunnels differ fundamentally from other types of tunnel (drill-and-blast, road header, hand-mined) due to the high level of machine-rock-rock stability interaction. In weak rock, especially if stresses are high, mucking and rock support may be the chief source of delay, and concrete element ring building may be compromised. In hard or very abrasive (quartz bearing) rock, equipment wear and cutter wear under the necessarily high loads will usually be the chief causes of reduced utilisation. Extreme water inflows may plague both on occasion.