Limitation of settlement of Klip River fill by surcharging

View at publisher
Authors: B.C. Van Wyk
Cited by: 0

Abstract

A 7m high fill was planned over the marshy Klip River for a 4 lane concrete highway. Maximum differential settlements of 3 mm per 4 m length could be tolerated. Surcharging was investigated as a solution. Notwithstanding a rather limited and unconventional investigation, good correlation with measured settlements were obtained.

Fields of Study & Subjects

Geotechnical Engineering and Soil Stabilization Geotechnical and construction materials studies Geotechnical Engineering and Soil Mechanics

Publication details

Journal / source
CRC Press eBooks
Pages
81–84
Publication date
14 January 2026
Language
EN