跨磁浮地铁大型钢连廊整体提升滑移施工技术

Read full text Summarise with VIRAT
Authors: 骜 黎
Cited by: 0

Summary

No summary yet. VIRAT can read this paper and write a plain-language summary of its aim, methods, key findings and limitations.

Summarise with VIRAT Free to try with your Science Catalogs account.

Abstract

在跨越运营中磁浮与地铁双轨的复杂环境下,大跨度钢连廊施工面临空间受限、时间紧迫及安全风险 高等多重挑战。本文通过利用移动提升设备及相关的施工工艺,对施工方法及流程进行合理优化,采用“远位拼 装,整体提升滑移落架”的施工方法,进行多专业一体化施工。该技术较大幅度的缩短施工工期,有效控制连廊的 安装精度,在保障运营安全的前提下完成施工,显著提升施工效率与工程可控性,为类似跨运营轨道工程提供重要 参考。