Optimalisasi Line Balancing pada Proses Produksi PCB Line KMM-X704KN PT. XYZ

Read full text Summarise with VIRAT
Authors: Rahmat Hidayat, Tri Ngudi Wiyatno, Dwi Indra Prasetya
Cited by: 0
References: 13

Summary

No summary yet. VIRAT can read this paper and write a plain-language summary of its aim, methods, key findings and limitations.

Summarise with VIRAT Free to try with your Science Catalogs account.

Abstract

This study aims to analyze and balance the production line in the assembly process using two Line Balancing methods, namely Helgeson–Birnie (H-B) and the Largest Candidate Rule (LCR), with a cycle time (CT) set at 2.28 minutes (137 seconds) based on the manual bottleneck workstation. The total element work time was recorded at 19.39 minutes, with a minimum required number of 9 workstations. The calculation results from both methods showed consistent and identical solutions, yielding 10 actual workstations (N_actual = 10). The line performance achieved a Line Efficiency (LE) of 85.04% with a Balance Delay (BD) of 14.96%. Although this efficiency is considered good, idle time analysis revealed a total waste of 3.41 minutes, most of which occurred at Workstation 10, which operated for only 0.20 minutes. These findings indicate that improvements should focus on restructuring the final workstation to eliminate waste, increase LE, and streamline total element time to approach the Takt Time, thereby optimizing overall line performance. This study provides practical recommendations for production management to enhance productivity and the efficiency of the assembly line.

Fields of Study & Subjects

Assembly Line Balancing Optimization Management and Optimization Techniques Advanced Queuing Theory Analysis