CONTROLLING SEQUENCE AND CONTROLLING ACTIVITIES IN THE REPETITIVE SCHEDULING METHOD

Read full text Summarise with VIRAT
Authors: Photios G. Ioannou, I‐Tung Yang
Cited by: 0

Summary

No summary yet. VIRAT can read this paper and write a plain-language summary of its aim, methods, key findings and limitations.

Summarise with VIRAT Free to try with your Science Catalogs account.

Abstract

The duration of target schedules produced by the Repetitive Scheduling Method (RSM) for both discrete and continuous repetitive projects is determined by a new concept, the controlling sequence, a continuous chain of controlling activities that span the project from start to finish. RSM scheduling and the identification of the controlling sequence are performed through the new concepts of controlling points and controlled points. The Trace Algorithm is introduced to (i) identify all controlling sequences and (ii) assign algebraic signs to controlling activities to connect them to (a) push-pull lean concepts, (b) project duration, (c) the RSM paradox, and (d) three new RSM scheduling principles. Proposed new bounds, Lo and Hi, define (a) production line segments belonging to multiple controlling sequences and (b) a new algorithm for identifying all controlling activities directly without tracing possibly billions of controlling sequences. The application of RP2, a program developed by the authors to identify controlling activities and critical activities in graphical and tabular reports, is illustrated by scheduling a complex of apartment buildings.

Fields of Study & Subjects

Resource-Constrained Project Scheduling Construction Project Management and Performance BIM and Construction Integration

Publication details

Publication date
21 March 2026
Language
EN